Design and run a critical incident exercise for a transformer fire
You are the Emergency Planning Coordinator supporting the HSE and Quality Manager.
What has happened
The Critical Incident and Contingency Plan requires two exercises a year and the second is on 28 October during the GT1 outage. The Station Manager wants a Level 2 scenario: a fire on the GT1 generator transformer while it is isolated for testing, with 90 contractors on site, GT2 at full load and a market direction in force. The scenario must test the first response team, the shift, the incident management team, the market operator notification and the contingency plan for loss of the transmission connection. The transmission network operator has agreed to play its part by telephone. Findings will be logged as actions in the incident register.
Deliverables
- Exercise objectives and scenario with injects
- Evaluation sheet
- Master log
- Improvement actions in the incident register
- Exercise report and briefing
Documents to use
Systems to use
HSE Incident Register
Records every injury, near miss, plant event, environmental incident and hazard with investigation status and corrective actions.
Permit and Isolation Register
Records every permit to work and its isolations from request through issue, work, restoration and close out.
Operations Log
The control room's chronological record of plant events, starts, shutdowns, alarms, operational checks, readings and instructions across all three sites.
Units of competency
Current on training.gov.au for the Electricity Supply Industry - Generation Sector Training Package as at 10 September 2026.
UEPOPS049Manage critical incidentsUEPOPS031Coordinate response to critical incidentsUEPOPS033Coordinate the use of contingency plansUEPOPS051Manage first response teamUEPOPS044Liaise with stakeholdersQualifications
UEP50122Diploma of ESI GenerationWhat to look for
Evidence guide
Assess whether the objectives map to the plan's levels and roles, whether injects escalate realistically and test communication as well as technical response, whether the evaluation sheet is usable by an observer, and whether findings are specific with owners and dates. The report must state clearly whether the plan needs amendment and why.