Audit the permit system after two near misses
You are the HSE Advisor reporting to the HSE and Quality Manager.
What has happened
Two near misses this month involved the permit system: the lube oil pump missing from the BFP-2B isolation list, caught at walk down, and a contractor scaffolder entering the GT1 fuel gas skid area without checking the permit board while the skid was depressurised for instrument work. The scaffolder event has no corrective actions recorded. Jordan Meyer wants the September permit audit done early, with every permit issued this month reviewed against the policy and the multiple energy source procedure, breaches recorded as incidents, and corrective actions with owners before the October outage brings 90 contractors to site.
Deliverables
- Audit criteria
- Findings per permit
- Incident register entries with actions
- Audit report
- Contractor briefing
Documents to use
Systems to use
Units of competency
Current on training.gov.au for the Electricity Supply Industry - Generation Sector Training Package as at 10 September 2026.
UEPOPS055Manage permit to work systemUEPOPS058Manage work health and safety policy and proceduresUEPOPS037Ensure compliance with work health and safety policy and proceduresUEPOPS056Manage quality control proceduresQualifications
UEP50122Diploma of ESI GenerationUEP40122Certificate IV in ESI GenerationWhat to look for
Evidence guide
Look for audit criteria drawn from the documents, permit by permit findings that cite the rule, correct classification of a missing energy source as a breach even though it was caught, corrective actions with owners and dates, and a report that identifies the common cause across the near misses. The contractor briefing must be practical and short.