Carry out dam safety surveillance and prepare the monthly report
You are the Hydro Operator at the Mitta Ranges station.
What has happened
Gallery drain D-14 at the Mitta Ranges concrete gravity dam has increased from 0.4 to 0.9 litres per minute over two months. The reading is below the alert level but the trend concerns the dam safety engineer, who wants a full instrument reading set and a written report this month. The storage is at 71 percent after winter rain and the hydro unit is out of service for governor work under OUT-26-09, so environmental flow is being released through the bypass valve. The weekly walkover, the piezometers, the seepage weirs and the survey points are all due. Two people must attend the gallery and the downstream toe.
Deliverables
- Inspection checklist and reading schedule
- Operations Log entries
- Updated incident register and work order records
- Monthly surveillance report
Documents to use
Systems to use
Operations Log
The control room's chronological record of plant events, starts, shutdowns, alarms, operational checks, readings and instructions across all three sites.
HSE Incident Register
Records every injury, near miss, plant event, environmental incident and hazard with investigation status and corrective actions.
Maintenance Work Orders and Defects
Holds every defect raised and every planned and corrective maintenance work order across the three sites with priority, crew and completion records.
Units of competency
Current on training.gov.au for the Electricity Supply Industry - Generation Sector Training Package as at 10 September 2026.
UEPOPS144Undertake dam safety surveillanceUEPOPS042Implement dam safety surveillance proceduresUEPOPS006Collect and analyse hydrological and meteorological dataUEPOPS018Conduct water conveyance and controlUEPOPS061Monitor and implement environmental site plans and proceduresQualifications
UEP30322Certificate III in ESI GenerationUEP40122Certificate IV in ESI GenerationWhat to look for
Evidence guide
Look for a walkover that covers every dam element in the procedure, readings compared to the previous reading and the alert level, correct escalation of the D-14 trend without overstatement, a report that separates observation from conclusion, and knowledge of the post-event triggers and the alert level response. The environmental flow must be logged, not assumed.